Europe’s battle for power leads to evolution of new power ecosystem


Electric grid is seen in Krakow Poland as Polish government lifts cup in electricity prices what is expected to rise inflation once more – January 18,2025. Poland has one of the highest inflations in Europe. (Photo by Dominika Zarzycka/NurPhoto via Getty Images)

Nurphoto | Nurphoto | Getty Images

The boom in artificial intelligence, a pressing need for more data centers and the energy transition story — particularly in transportation — are all spurring demand for electricity, and the existing power infrastructure is struggling to keep up.

Businesses are facing five to eight-year wait times to connect to Europe’s ageing and strained electricity grids, experts told CNBC, as the emergence of new areas of demand drives an unprecedented rise in permit requests for power. According to the IEA, at least 1,500 gigawatts of global clean energy projects have been stopped or delayed because of a lack of grid connections and about $700 billion of grid investment is needed for countries to meet their green goals.

Data centers, the large facilities that house servers for computing processes and often require huge amounts of power, are the “primary director” of that growing competition to connect to the grid, said Diego Hernandez Diaz, partner at McKinsey.

He told CNBC that clients have quoted wait times of up to eight years to connect to the grid.

“There are certain transmission system operators in Europe, that are already facing two, three or more folks all attempting to interconnect to the same node at the same time. … There is a literal queue within individual connection points to see who gets to connect first,” he explained.

Europe’s battle for power spurs evolution of a new ecosystem for data centers

Hernandez, whose work focuses on electro-intensive industries, said that over the last 18 months, nearly all of his work has focused on data centers, a sector that he expects to grow at an annual compound growth rate of 20% over the next six years. Demand for the facilities required to train large language models (LLMs) is expected to continue its exponential increase as tech giants race to dominate in AI.

Energy management firm Schneider Electric warned in a January report that Europe faces a looming power crunch, with three to five-year waiting lists for grid connections in energy-constrained regions.

“It’s kind of a race,” Steven Carlini, chief advocate of AI and data centers at Schneider Electric, told CNBC. “You have all these companies that are trying to deploy as much capacity as they can. But it’s constrained by the number of GPUs [graphics processing units] and the available power and the permitting.”

“We’re going from a situation where you have one application or two applications [to connect to the grid] per year, in some countries, to 1,000,” Carlini said.

It’s not just the amount of investment needed — but also the speed with which it can be deployed — which will be key to addressing the issue, McKinsey’s Diaz said. He also pointed to the growing complexity of the work of high-voltage grid operators and the example of Germany, which needs to go from building 400 kilometers of power lines a year to 2,000 kilometers.

We’re going from a situation where you have one application or two applications per year, in some countries to 1,000.

Steven Carlini

Chief advocate of AI and data center

Diaz sees the competition to connect to the grid “either maintaining or intensifying” in 2025.

Jerome Fournier, vice president of innovation at subsea cable manufacturer Nexans, said his firm has a “huge” order backlog in the range of seven-to-10 billion euros ($7.28 billion-$10.40 billion). Nexans’ cables are used to transmit electricity generated by wind and solar farms, and to supply power to homes and businesses.

“Everybody’s considering: do we still have some room in our plans to manufacture other projects?” he said.

Fournier told CNBC that firms like Nexans should also keep slots available for smaller projects such as interconnections for offshore wind turbines. “You’ve got to have the right balance between the load of the plans, the profitability and this type of electrification,” he said.

A new power ecosystem

Power constraints are leading data center operators to evolve their own “ecosystem of power backup,” according to Schneider Electric’s Carlini.

In the future, data centers are expected to be at the center of that grid ecosystem, particularly if they are able to generate their own power with small modular reactors — mini nuclear reactors that produce electricity.

Battery storage and strategic charging are also becoming increasingly important, Carlini said. These systems allow for the temporary storage of energy from the power grid to provide extra backup.

The CEO of power solutions provider AVK, Ben Pritchard, said some European countries are facing large, 100-megawatt grid connection requests of a size…



Read More: Europe’s battle for power leads to evolution of new power ecosystem

Subscribe
Notify of
guest
0 Comments
Oldest
Newest Most Voted
Inline Feedbacks
View all comments

Get more stuff like this
in your inbox

Subscribe to our mailing list and get interesting stuff and updates to your email inbox.

Thank you for subscribing.

Something went wrong.